A1 Motorway Kowal to Sojki

  • Contract Value: €168 Million
  • Contract Type: Polish FIDIC Red Book (2000 Edition)
  • Client: Polish GDDKiA
  • Start/End: September 2010 - September 2012
  • Company Involvement: Roadbridge as part of the SRB-Budbaum consortium was nominated preferred tenderer summer 2010

View project PDF

The project consisted of the construction of 29.95km of motorway in the Polish countryside. The scope of works included 610,000 Tons of Bituminous Macadam, 992m. precast box culverts and 230m pipe culverts. There were 2 no. Interchanges, Utility diversions, Lighting, emergency telephones, motorway communications, Signing and Marking.

Key Features

  • 1,150,000 m3 of cut and 1,805,000 m3 import
  • 17 no. bridge structures
  • 2 no. Motorway service area (MOP Lubien & MOP Strzelce) and 2 no. Toll Plazas (SPO Kowal & SPO Sojki)
  • Environmental protection works including 67,000m2 of acoustic barrier 3m to 6.5m high
  • 21 no. Insitu Concrete Animal Passes and 18 no. Precast Concrete Animal Passes