Harehill Windfarm Extension

  • Contract Value: £7.3 Million
  • Contract Type: IEC - FIDIC
  • Client: Iberdrola Engineering and Construction
  • Start/End: March 2016 - September 2016
  • Company Involvement: Roadbridge was appointed as Contractor for this project in February 2016. Iberdrola are acting as the Principal Contractor on the project.

View project PDF

This project involves the construction of a windfarm consisting of 35 Nr. WTG Bases and Hardstands, with a total output of 29.75MW, close to New Cumnock in East Ayrshire, Scotland. The project also includes the crossing of 2 Nr. Registered Water Crossings.

Key Features

  • Construction of 35 Nr. WTG Bases and Hardstands
  • Construction of 14km and Upgrade of 5km of Access Roads
  • Operation of 3 Borrow Pits as per Quarry Regulations 1999 and onsite processing of materials
  • Installation of 12km of cable trenching
  • Construction of 1 Nr. Substation Platform