Belmullet Sewerage Scheme DBO

  • Project Type Wastewater
  • Client Irish Water
  • Company Involvement Roadbridge acted as Main Contractor and PSCS for the construction of the pipelines pumping stations, EPS were PDSP and carried out the M&E works. Roadbridge EPS JV continue to work as Operators for the plant.
  • Form of Contract FIDIC Gold Book (Design, Build, Operate)
  • Dates June 2016 - December 2017
  • Location Co. Mayo, Ireland



Key Features

  • Design and Construct 3.5km rising main sewers
  • Design and Construct 1.5km of gravity sewer
  • Design and Construct 2 No. pumping stations(with operations building and control kiosk)
  • Design and Construct 250m long horizontal directional drill to cross under an existing canal and close proximity to existing dwellings where open cut wasn’t possible
  • Design and Construct a Waste Water Treatment Plant with a population equivalent (PE) of 2500
  • Associated services including house connections, ESB ducting
  • Design and Construct a 600M marine outfall
  • Design and Construct a new wastewater treatment plant operations building
  • Rehabilitation of existing sewers
  • Upon completion of commissioning for the new treatment plant RB-EPS JV took over operations of the treatment plant for the initial 2 year operation period (as part of the DBO works)