Back to projects overview

Cadbury Schweppes- Enabling & Ground Works Package

  • Project Type Industrial / Commercial
  • Client Cadbury Ireland Ltd
  • Company Involvement Roadbridge Ltd was awarded the enabling & ground works package for the Cadbury Schweppes site development in June 2004. Bovis Lend Lease was the designer for this project.
  • Form of Contract IEI Contract
  • Dates June 2004 - December 2004
  • Location Dublin, Ireland
  • Value €1.3 Million


View project PDF

The main marine works for the contract consisted of the construction of a 475m 800mmØ HDPE sea outfall pipeline as follows:


Key Features

  • Bulk excavation to reduced levels of approximately 12,000m³
  • Service installation including: Foul and Surface water drainage ranging from 150-375mm diameter up to 2.5m deep (700m), 150mm watermain (200m), 250mm fire main (500m), 100-150mm ducting 1-10 way (2,300m), Gas installation (65m)
  • Installation of pad foundations, ground beams and raft foundations (1,600m³ of concrete)