Back to projects overview

Demolition of Lead-In Jetty at Alexandra Quay West

  • Contract Type NEC3 Option B
  • Client Dublin Port Company (DPC)
  • Company Involvement The project involves the demolition and disposal of an existing jetty at Alexandra Quay West. Works undertaken by the Roadbridge and L&M Keating Joint Venture.
  • Start / End Dates 6 March 2017 – 5 May 2018
  • Contract Value €0.97 Million


View project PDF

The works will be conducted in several phases to avoid disruption to current port operations.

The works comprise of:


Key Features

  • The removal of one pedestrian walkway bridge
  • Demolition of concrete slab and supporting caissons.
  • Removal of steel piles retaining structures.
  • Loading, hauling and disposal of the materials by road to national reception sites.
  • Reinstatement of seabed.