Design and Construction of Apron Slab Berth 26 & Berth 27

  • Contract Type NEC3 Option B
  • Client Dublin Port Company (DPC)
  • Company Involvement The project involves the design and construction of apron slab for port operations including container loading on Berths 26 &27 Works undertaken by the Roadbridge and L&M Keating Joint Venture with design works by Malachy Walsh and Partners.
  • Start / End Dates Design commenced 5 May 2017 with construction 21 September 2017 – 16 December 2017
  • Contract Value €1.75 Million


View project PDF

The works comprise of design and construction of the following elements, with design to cater for expected settlements in apron slab and with traverse movements in adjoining quay wall.


Key Features

  • Water main and communication utilities
  • Drainage pipework, gullies and hydro block channels
  • Chambers, manholes and inspection boxes for services
  • Installation of subbase, blinding and concrete for 4,700m2 yard slab with depths varying from 600mm deep to 900mm deep.
  • Installation of all ironmongery to F900 loading.