Eli Lilly S.A. – Infrastructure 1 Contract

  • Project Type Industrial / Commercial
  • Client Eli Lilly S.A
  • Company Involvement Roadbridge completed elements of the Eli Lilly Earthworks & Foundations Contract from March - October 2004.
  • Form of Contract IEI Subcontract
  • Dates December 2004 - November 2006
  • Location Co. Cork, Ireland
  • Value €4.3 Million


View project PDF

Key Features

  • Site clearance of approx. 5.6 acres including 70,000m 3 of topsoil
  • The excavation of 67,400m³ of clay and 8,700m³ of rock to soil deposition areas for re-use
  • Disposal of 83,000m³ of excavated material off-site
  • 6,470m² of pavement surfacing for Roads
  • 5,578m² of pavement surfacing to car parks
  • Over 4km of drainage from 600mm to 150mmØ pipes
  • 5,531m of 160mmØ ducting
  • 512m of Ductile Iron Watermain and associated Fittings
  • Construction of Plinths and Bases for Main Building Works for Biotech Manufacturing
  • 800m² insitu retaining wall of max height 9m and 100m long
  • Landscaping and verge finishing of 8,000m²