Back to projects overview

Galmoy Tailings Dam – Phase 2

  • Project Type Mining
  • Client Arcon Mines Ltd
  • Company Involvement The Galmoy Tailings Dam project was awarded to Roadbridge in November 1999Roadbridge undertook the position of Main Contractor.
  • Form of Contract Traditional
  • Dates November 1999 - September 2000
  • Location Co. Kilkenny, Ireland



Key Features

  • Demolition and Site Clearance
  • 580,000m3 of Earthworks in dam construction
  • 4km access road on top and bottom of dam
  • Installation of 150,000m2 of Geogrid, Geotextile and Geomembrane
  • 32km of Containment Drainage
  • Installation of Piezometer and other monitoring equipment
  • 3km Tailings Pipeline
  • Enabling Electrical Works