Back to projects overview

Harehill Windfarm Extension

  • Project Type Wind
  • Client Iberdrola Engineering & Construction
  • Company Involvement Roadbridge was appointed as the contractor for this project in February 2016.
  • Form of Contract IEC - FIDIC
  • Dates March 2016 – September 2016
  • Location New Cumnock, Scotland


All civils works associated with the construction of a 29.7MW Windfarm


Key Features

  • Excavate and construction of 35 no. bases and hardstands completed in 12 weeks
  • Constructed 14km of access roads
  • Upgrade of 5km of Access Roads
  • Operation of 3 Borrow Pits as per Quarry Regulations 1999 and onsite processing of materials
  • 12km of Cable Trenching
  • 1 no. Turbine Contractor Platform
  • 1 no. Substation Platform
  • 2 no. Registered Water Crossings