The infrastructure package for Langley Court was awarded to Roadbridge in September 2015, the works comprised of design and construction for all infrastructure works for the residential development of Langley Court
-
Form of Contract
JCT Design & Build
-
Dates
October 2015 – August 2016
-
Location
London, United Kingdom
Key Features
- Construction of all site infrastructure, access roads and footpaths
- 1km of gravity clay sewer, with connection to existing public network
- 1km of surface water network with attenuation pond and 3 no. percolation impoundment pits and geocellullar storage
- Hard landscaping brick pavement 5,500m2
- New HV Substation, adopted by UK power networks
- 3 no. Timber footbridges and associated abutments and gabion faced wall
- Substructure works for future raised timber boardwalk around lake feature
- Soft landscaping works with 120 new trees, 1km of formal hedgerows, and 15,000m2 of fine lawns
- New playground with Bandstand and gardens
- This project was completed within the required programme and budget