Back to projects overview

Lot C23 A41 Break from Highways

  • Project Type Rail
  • Client EKFB (Eiffage, Kier, Ferrovial and BAM)
  • Company Involvement Civil Enabling Works Subcontractor to EKFB
  • Form of Contract Short Form Cost Reimbursable Contract
  • Dates December 2020 - September 2021
  • Location Aylesbury


This enabling works project carried out as part of the HS2 project for EKFB JV entailed the construction of a site access from the A41, access road to the site and the establishment of a site compound for the main works


Key Features

  • 1.5km of Boundary Fencing (Heras Fencing)
  • Excavation of temporary drainage V-ditch (600m) and provision of 1 No. Attenuation Pond (1200 m3)
  • Earthworks of 14,000m3 including topsoil strip and cutting
  • Temporary Welfare and offices set-up including all hardstanding and car park areas
  • Installation of permanent drainage (buried pipes, Manholes and Road gullies)
  • Surfacing along access road
  • Kerbing
  • Road Surfacing
  • Tie-ins on the Existing A41 during Road Closure
  • Site environmental works including provision of silt buster for water treatment.