This contract comprised the design and construction of 40km 2-lane motorway with 4 Interchanges and extensive earthworks, drainage, structures & traffic management through sensitive habitat including a number of cSACs. Principle quantities comprised 4.7M m³ earthworks (including300,000m3 of Peat, 1,100,000m³ rock excavation). 1 million m² of pavement, 53 no. culverts, landscaping, utilities accommodation works and other ancillary works.
The project was completed 7 months ahead of time.