Removal of Legacy Materials Berth 52-53

  • Contract Type NEC3 Option B
  • Client Dublin Port Company (DPC)
  • Company Involvement The project involves the removal of 35,000tons of legacy materials from Berth 52-53 Works undertaken by the Roadbridge and L&M Keating Joint Venture.
  • Start / End Dates 20 July 2017 – 11 Nov 2017
  • Contract Value €2.31 Million


View project PDF

The works comprise of the following, as well as the provision of a comprehensive materials report for the life cycle assessment (cradle to grave) of the materials.


Key Features

  • Selecting and segregating stockpiles of legacy materials
  • Sampling and analysis of the materials
  • Classification into waste streams and categorization.
  • Loading, hauling and disposal of the materials by road to national reception sites and by sea to international disposal sites.
  • Monitoring waste removals, facility licenses and Trans frontier shipping permits.