Seagreen Landfall Works

  • Project Type Marine
  • Client Nexans Norway
  • Company Involvement Temporary Works Design and Construction
  • Form of Contract Bespoke Subcontract - Based stepped down FIDIC Conditions
  • Dates December 2020 - July 2021
  • Location Carnoustie, Dundee


Full temporary design and construction of landfall cofferdam and associated civils works including open trench works for onshore and offshore export cabling


Key Features

  • Works undertaken during the early stages of the Covid-19 Pandemic under strict health and safety protocols resulting in zero infections on site
  • Phased construction of cofferdam including shoreline working platform on installed sheet piling
  • Breaking through existing shoreline revetment and reinstatement of revetment post installation works
  • Civil works on duct installation for Landfall connection with Onshore cable works to incoming sub-sea cables
  • Final reinstatements under strict environmental conditions of the beach and adjacent international championship golf course