Upper Liffey Valley Sewerage Scheme – Contract 2A
-
Project Type
Wastewater
-
Client
Irish Water
-
Company Involvement
Roadbridge was appointed as the Main Contractor and PSCS for this project in March 2019.
-
Form of Contract
Irish Water - Major Works Civil Engineering Contract – Design and Construction
-
Dates
March 2019 – May 2021
-
Location
Newbridge to Naas, Ireland
Key Features
- Kilbelin Pumping station - Civil and M&E works and 2,000 m3 storm tank
- Little connell Pumping station - Civil and M&E works and 1,800 m3 storm tank
- Newhall Pumping Station - Civil and M&E works and 1,800 m3 storm tank
- 3.1km of gravity sewers (900 & 1,050mm);
- 4.5km of rising mains (600 & 700mm
- Twin 200m long 560mm OD directional drill under the River Liffey
- 12-month operate phase for 3 Pumping Stations